Kista Gate PoP migration phase 2

Scheduled Maintenance Report for SONIX

Completed

The scheduled maintenance has been completed.
Posted Feb 26, 2026 - 01:00 CET

Update

Scheduled maintenance is still in progress. We will provide updates as necessary.
Posted Feb 26, 2026 - 00:45 CET

Update

PoPs at Stokab KN7, City Hosting, and Equinix SK2 are operational again, including the Stockholm Route Servers and IXP-Manager. We are extending the maintenance window by one additional hour for Obenet Kista Gate (ixp-kg-sw2) while we restore member ports sequentially.
Posted Feb 26, 2026 - 00:44 CET

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Feb 25, 2026 - 17:00 CET

Scheduled

This Wednesday we will perform Phase 2 of our staged migration, including cutover activities for Obenet Kista Gate (ixp-kg-sw2) PoP. Stockholm Route Servers and IXP Manager will experience extended periods of unavailability during the maintenance window.

This work will also impact the PoPs Stokab KN7, City Hosting, and Equinix SK2. Traffic will be culled according to RFC 8327 before data plane disruption to avoid impact for multi-homed members.

Note: we are retiring ixp-kg-sw1 and migrating any 100GBASE-CWDM4 media to 100GBASE-FR1 on our side.
Posted Feb 23, 2026 - 00:06 CET
This scheduled maintenance affected: IX Platform (Obenet Kista Gate, Stokab KN7, City Hosting, Equinix SK2), IXP Manager, and Route Servers (Stockholm).